Your construction project is located within 500 feet of a designated wetland area. Which agency approval will likely be required before beginning construction?
Correct Answer
B) Florida Department of Environmental Protection
The Florida Department of Environmental Protection (DEP) regulates activities near wetlands and would require permits for construction projects that may impact these protected areas.
Why This Is the Correct Answer
The Florida Department of Environmental Protection (DEP) is the state agency responsible for protecting Florida's natural resources, including wetlands. Construction projects within 500 feet of designated wetlands typically require environmental permits and impact assessments. The DEP has jurisdiction over wetland protection and regulates activities that could potentially disturb or contaminate these sensitive ecosystems. Any construction near wetlands must comply with state environmental regulations administered by this agency.
Why the Other Options Are Wrong
Option A: Florida Department of Transportation
The Florida Department of Transportation (FDOT) primarily handles transportation infrastructure, roadways, and related construction projects, not environmental protection or wetland regulation.
Option C: Florida Department of Agriculture
The Florida Department of Agriculture focuses on agricultural activities, food safety, and consumer protection, not environmental permitting for construction near wetlands.
Option D: Florida Department of Economic Opportunity
The Florida Department of Economic Opportunity handles workforce development, economic development programs, and emergency management, not environmental protection or wetland permits.
Memory Technique
DEP = Don't Endanger Protected areas. When you see wetlands mentioned, think DEP for environmental protection.
Reference Hint
Florida Building Code Chapter 1, Administrative provisions, or Environmental regulations section - look for wetland protection and permitting requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass