Project documentation shows that a structural beam was relocated 2 feet north from its original design position due to a field conflict. This change was approved by the structural engineer. How should this be reflected in project closeout documents?
Correct Answer
B) Update the as-built drawings to show actual location
Approved field changes must be reflected in as-built drawings to show the actual constructed conditions. This ensures future maintenance and renovation work has accurate information.
Why This Is the Correct Answer
As-built drawings are the official record of how the project was actually constructed, not how it was originally designed. When approved field changes occur, such as relocating a structural beam, these modifications must be documented in the as-built drawings to reflect the true constructed conditions. This ensures that future maintenance, renovations, or emergency work will have accurate information about the actual location of structural elements. As-built drawings are a critical component of project closeout documentation and serve as the permanent record for the facility owner.
Why the Other Options Are Wrong
Option A: Note the change in the project diary only
While project diaries are important for daily documentation, they are not sufficient for recording permanent changes to the constructed work. Project diaries are typically temporary records used during construction, whereas structural changes need to be permanently documented in drawings that will be used for future reference.
Option C: Include only in the change order log
Change order logs track the administrative and financial aspects of changes but do not provide the technical details of actual constructed conditions. While the change should be included in the change order log, this alone is insufficient - the actual location must be shown graphically in the as-built drawings.
Option D: Document in meeting minutes but not on drawings
Meeting minutes document discussions and decisions but do not provide the precise technical information needed for future work. Like change order logs, meeting minutes are administrative records that supplement but cannot replace the technical accuracy required in as-built drawings.
Memory Technique
Think 'AS-BUILT = AS-ACTUALLY-BUILT' - if it changed in the field, it must change on the as-built drawings
Reference Hint
Florida Building Code - Chapter 1, Section 107 (Submittal Documents) and AIA Document A201 - General Conditions, Article 3.11 (As-Built Documents)
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass