During a renovation project, workers discover materials suspected to contain asbestos. What is the first action the general contractor should take?
Correct Answer
B) Stop work immediately and have the material tested by a certified laboratory
When asbestos-containing materials are suspected, work must stop immediately and the material must be tested by a certified laboratory. Only certified abatement professionals should handle confirmed asbestos materials.
Why This Is the Correct Answer
Option B is correct because federal and state regulations require immediate work stoppage when asbestos-containing materials are suspected. The material must be tested by a certified laboratory to confirm the presence of asbestos before any further action can be taken. This protects workers and occupants from potentially deadly asbestos exposure. Only after proper testing and identification can appropriate abatement procedures be implemented by certified professionals.
Why the Other Options Are Wrong
Option A: Continue work while wearing N95 respirators
N95 respirators provide insufficient protection against asbestos fibers, which require specialized HEPA filtration. Continuing work while suspected asbestos is present violates OSHA regulations and puts workers at serious health risk.
Option C: Wet the material and remove it carefully
Wetting and removing suspected asbestos materials without proper testing and certification is illegal and extremely dangerous. This action could release deadly fibers into the air and contaminate the entire work area.
Option D: Seal the area with plastic sheeting and continue working in other areas
Plastic sheeting alone cannot contain asbestos fibers, and continuing work in other areas while suspected asbestos is present violates safety protocols. The entire project must stop until proper testing is completed.
Memory Technique
Think 'ASBESTOS = ALWAYS STOP, TEST FIRST' - the 'S' in asbestos reminds you to STOP, and you can't spell TEST without the 'T' that follows.
Reference Hint
Florida Building Code Chapter 1, Section 107 - Submittal Documents, and OSHA 29 CFR 1926.1101 for asbestos construction standards
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass