A LEED Gold certified building project requires 30% water use reduction compared to baseline. The baseline water use is calculated at 120,000 gallons per year. What is the maximum allowable annual water use?
Correct Answer
A) 84,000 gallons
A 30% reduction means the building can use only 70% of baseline consumption. 120,000 × 0.70 = 84,000 gallons per year maximum allowable use.
Why This Is the Correct Answer
When LEED requires a 30% water use reduction, this means the building must use 30% LESS water than the baseline, not 30% of the baseline. Therefore, the maximum allowable use is 70% of the original baseline consumption. The calculation is straightforward: 120,000 gallons × 0.70 = 84,000 gallons per year. This represents a 36,000 gallon reduction from the baseline, which equals exactly 30% of 120,000 gallons.
Why the Other Options Are Wrong
Option B: 90,000 gallons
This represents a 25% reduction (120,000 - 90,000 = 30,000, which is 25% of 120,000), not the required 30% reduction for LEED Gold certification.
Option C: 96,000 gallons
This represents only a 20% reduction (120,000 - 96,000 = 24,000, which is 20% of 120,000), falling short of the 30% requirement.
Option D: 108,000 gallons
This represents only a 10% reduction (120,000 - 108,000 = 12,000, which is 10% of 120,000), significantly below the 30% LEED requirement.
Memory Technique
Think 'REDUCE and REMAINDER': If you reduce by 30%, the remainder is 70%. Always calculate what remains, not what's removed.
Reference Hint
Florida Building Code, Chapter 13 - Energy Efficiency, and LEED reference materials in the green building sections
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A contractor is building a shopping center that requires 150 parking spaces. If the zoning ordinance requires 1 parking space per 250 square feet of retail space, what is the maximum allowable retail square footage?
Next Question
In LEED projects, what is the primary benefit of implementing a construction waste management plan?