EstatePass
Contract AdminPermitshard20% of exam part

A contractor applies for a building permit on Monday. The local building department has 30 calendar days to review the application. If no response is received by the deadline, what happens to the permit application?

Correct Answer

B) The application is automatically approved

Under Florida law, if a building department does not respond to a permit application within the specified timeframe (typically 30 days), the application is deemed automatically approved. This prevents unnecessary delays in the permitting process.

Answer Options
A
The application is automatically denied
B
The application is automatically approved
C
The review period is extended by 15 days
D
The contractor must resubmit the application

Why This Is the Correct Answer

Florida Statutes Section 125.022 and 166.033 establish the 'deemed approved' rule for building permits. This statutory provision ensures that local governments cannot indefinitely delay construction projects by failing to act on permit applications. The automatic approval mechanism protects contractors and property owners from bureaucratic delays while still allowing reasonable time for proper review. This rule applies when the building department fails to approve, approve with conditions, or deny the application within the specified timeframe.

Why the Other Options Are Wrong

Option A: The application is automatically denied

Automatic denial would be counterproductive and unfair to applicants, as it would penalize them for the building department's failure to act timely. Florida law specifically protects against this outcome.

Option C: The review period is extended by 15 days

There is no provision in Florida law for automatic extensions of the review period. The 30-day timeframe is firm, and failure to act results in deemed approval, not extended review time.

Option D: The contractor must resubmit the application

Requiring resubmission would create an endless loop that could allow building departments to indefinitely delay projects by simply not responding. Florida law prevents this by making approval automatic.

Memory Technique

Think 'No News is Good News' - when the building department gives you no response by the deadline, that's good news because it means automatic approval.

Reference Hint

Florida Statutes Chapter 125.022 (counties) and 166.033 (municipalities) - Local Government Comprehensive Planning sections

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing