In a CPM schedule, Activity A has a duration of 5 days, Activity B has 8 days, and Activity C has 6 days. If A and B can run concurrently, and C follows both A and B, what is the total project duration?
Correct Answer
A) 14 days
Since A (5 days) and B (8 days) run concurrently, the longest duration is 8 days. Activity C (6 days) follows both, so total duration is 8 + 6 = 14 days.
Why This Is the Correct Answer
In CPM scheduling, when activities run concurrently (in parallel), you take the longest duration of the concurrent activities. Activities A (5 days) and B (8 days) run simultaneously, so this phase takes 8 days (the longer of the two). Activity C (6 days) cannot start until both A and B are complete, so it adds sequentially to the 8-day concurrent phase. The total project duration is therefore 8 + 6 = 14 days.
Why the Other Options Are Wrong
Option B: 19 days
19 days would be the result if you incorrectly added all three activities sequentially (5 + 8 + 6 = 19), ignoring the fact that A and B run concurrently and should not both be counted in the total duration.
Option C: 11 days
11 days would be the result if you incorrectly took the shorter concurrent activity duration (A = 5 days) and added C (5 + 6 = 11), rather than using the longer concurrent activity duration (B = 8 days).
Option D: 8 days
8 days only accounts for the concurrent phase duration and completely ignores Activity C, which must be completed after both A and B are finished.
More Business & Finance Questions
A contractor's license expires on March 31st. If they submit a renewal application on April 15th, what additional requirement must be met under Florida regulations?
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
In Florida, what is the minimum workers' compensation insurance coverage required for construction companies with employees?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?