During renovation of a building constructed in 1965, friable asbestos is discovered. What is the minimum notification period required before beginning abatement work in Florida?
Correct Answer
B) 10 working days
Florida requires a minimum 10 working day notification to the Department of Environmental Protection before beginning asbestos abatement work. This allows time for proper review and inspection scheduling.
Why This Is the Correct Answer
Florida Statute 469.003 and DEP regulations require a minimum 10 working day advance notification to the Department of Environmental Protection before beginning any asbestos abatement work. This notification period allows DEP sufficient time to review the abatement plan, schedule inspections, and ensure proper procedures will be followed. The 10-day requirement is specifically for friable asbestos removal and applies to all renovation and demolition projects where asbestos-containing materials will be disturbed.
Why the Other Options Are Wrong
Option A: 5 working days
5 working days is insufficient under Florida law and would not provide adequate time for DEP review and inspection scheduling
Option C: 15 working days
15 working days exceeds the minimum requirement and could unnecessarily delay construction projects
Option D: 20 working days
20 working days is excessive and would create unreasonable project delays beyond what Florida law requires
Memory Technique
Think 'Perfect 10' - Florida requires a perfect 10 working days for asbestos abatement notification, just like a perfect gymnastics score
Reference Hint
Florida Building Code Chapter 4 - Special Detailed Requirements Based on Use and Occupancy, Section on Hazardous Materials, or Florida Statute 469.003
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Previous Question
A site plan shows a building setback dimension of 25'-0" from the property line, but the survey shows the building is actually 23'-6" from the line. What is the most appropriate action?
Next Question
You receive shop drawings for structural steel that show connections different from the original design. The drawings are stamped by a Florida licensed engineer. What is your responsibility as the general contractor?