You're expediting concrete delivery for a critical pour scheduled for Monday. The supplier informs you Friday that they cannot deliver until Tuesday due to equipment breakdown. What is your best course of action?
Correct Answer
C) Find an alternate supplier immediately for Monday delivery
For critical activities, finding an alternate supplier to maintain the schedule is typically the best option. This prevents delays to the critical path and maintains project momentum, even if costs may be higher.
Why This Is the Correct Answer
Finding an alternate supplier immediately is the best option because the concrete pour is described as 'critical,' meaning it's likely on the critical path of the project schedule. Delaying critical activities causes project delays, which can result in significant costs, penalties, and cascading schedule impacts. Even if the alternate supplier costs more, maintaining the schedule prevents much larger financial and contractual consequences that come with project delays.
Why the Other Options Are Wrong
Option A: Delay the pour until Tuesday and adjust the schedule
Negotiating penalty payments doesn't solve the immediate problem of needing concrete for Monday's critical pour. While you may pursue penalties later, the priority must be maintaining the project schedule to avoid much larger delay costs and contractual penalties.
Option B: Negotiate penalty payments from the original supplier
Delaying the pour until Tuesday would push back the critical path activity, causing project delays that could trigger liquidated damages, extend overhead costs, and delay subsequent trades. The ripple effect of delaying critical activities typically costs far more than finding alternative solutions.
Option D: Split the order between multiple suppliers
Splitting orders between multiple suppliers introduces coordination complexity, potential quality control issues from different mix designs, and timing challenges that could jeopardize the pour quality. This approach also doesn't guarantee Monday delivery and adds unnecessary risk to a critical activity.
Memory Technique
Remember 'CRITICAL = CAN'T WAIT' - critical path activities must proceed on schedule regardless of cost premiums to avoid project delays
Reference Hint
Project Management/Scheduling chapter - Critical Path Method (CPM) and schedule compression techniques
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?