Your project has a critical path of 85 days. You can crash Activity X (on critical path) from 12 days to 9 days for an additional cost of $15,000. The project has a delay penalty of $2,000 per day. Should you crash this activity?
Correct Answer
B) No, it costs an extra $9,000
Crashing saves 3 days (12-9), avoiding $6,000 in penalties (3 × $2,000). However, crashing costs $15,000. Net cost = $15,000 - $6,000 = $9,000 extra expense, so crashing is not economical.
Why This Is the Correct Answer
Option B is correct because the cost-benefit analysis shows crashing is not economical. While crashing Activity X saves 3 days and avoids $6,000 in delay penalties, it costs $15,000 to implement. The net result is a $9,000 additional expense ($15,000 cost - $6,000 savings), making crashing financially unfavorable. Therefore, the contractor should not crash this activity.
Why the Other Options Are Wrong
Option A: Yes, it saves $3,000
Option A incorrectly states that crashing saves $3,000. This fails to account for the full cost of crashing ($15,000) and only considers partial savings, leading to an incorrect financial conclusion.
Option C: The decision depends on other factors not provided
Option D is wrong because all necessary information is provided to make the decision. The crash cost ($15,000), time savings (3 days), and penalty rate ($2,000/day) give sufficient data for a complete cost-benefit analysis.
Option D: Yes, it saves $6,000
Option C incorrectly states that crashing saves $6,000. While $6,000 represents the penalty savings from reducing the schedule by 3 days, it ignores the $15,000 cost to crash the activity, resulting in a net loss rather than savings.
Memory Technique
Remember 'CRASH = Cost minus Reduction benefits' - if the crash cost is higher than penalty reduction benefits, don't crash the activity.
Reference Hint
Project Management chapter, specifically sections on Critical Path Method (CPM) and project crashing/time-cost trade-offs
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
