EstatePass
Business & FinanceOperationshard10% of exam part

Your project has a critical path of 85 days. You can crash Activity X (on critical path) from 12 days to 9 days for an additional cost of $15,000. The project has a delay penalty of $2,000 per day. Should you crash this activity?

Correct Answer

B) No, it costs an extra $9,000

Crashing saves 3 days (12-9), avoiding $6,000 in penalties (3 × $2,000). However, crashing costs $15,000. Net cost = $15,000 - $6,000 = $9,000 extra expense, so crashing is not economical.

Answer Options
A
Yes, it saves $3,000
B
No, it costs an extra $9,000
C
The decision depends on other factors not provided
D
Yes, it saves $6,000

Why This Is the Correct Answer

Option B is correct because the cost-benefit analysis shows crashing is not economical. While crashing Activity X saves 3 days and avoids $6,000 in delay penalties, it costs $15,000 to implement. The net result is a $9,000 additional expense ($15,000 cost - $6,000 savings), making crashing financially unfavorable. Therefore, the contractor should not crash this activity.

Why the Other Options Are Wrong

Option A: Yes, it saves $3,000

Option A incorrectly states that crashing saves $3,000. This fails to account for the full cost of crashing ($15,000) and only considers partial savings, leading to an incorrect financial conclusion.

Option C: The decision depends on other factors not provided

Option D is wrong because all necessary information is provided to make the decision. The crash cost ($15,000), time savings (3 days), and penalty rate ($2,000/day) give sufficient data for a complete cost-benefit analysis.

Option D: Yes, it saves $6,000

Option C incorrectly states that crashing saves $6,000. While $6,000 represents the penalty savings from reducing the schedule by 3 days, it ignores the $15,000 cost to crash the activity, resulting in a net loss rather than savings.

Memory Technique

Remember 'CRASH = Cost minus Reduction benefits' - if the crash cost is higher than penalty reduction benefits, don't crash the activity.

Reference Hint

Project Management chapter, specifically sections on Critical Path Method (CPM) and project crashing/time-cost trade-offs

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.