Your company is managing inventory for a large commercial project. The Economic Order Quantity (EOQ) for concrete blocks is 2,400 units. If annual demand is 28,800 units, how many orders should be placed per year?

Correct Answer

B) 12 orders

Number of orders = Annual demand ÷ EOQ = 28,800 ÷ 2,400 = 12 orders per year. This calculation helps determine ordering frequency for optimal inventory management.

Answer Options
A
8 orders
B
12 orders
C
20 orders
D
15 orders

Why This Is the Correct Answer

The correct answer is B (12 orders) because the number of orders per year is calculated by dividing the annual demand by the Economic Order Quantity (EOQ). With an annual demand of 28,800 units and an EOQ of 2,400 units, the calculation is 28,800 ÷ 2,400 = 12 orders. This formula ensures optimal inventory management by determining how frequently orders should be placed to minimize total inventory costs while meeting project demands.

Why the Other Options Are Wrong

Option A: 8 orders

Option A (8 orders) would result from incorrectly calculating 28,800 ÷ 3,600, suggesting an EOQ of 3,600 units rather than the given 2,400 units.

Option C: 20 orders

Option D (20 orders) would result from incorrectly calculating 28,800 ÷ 1,440, suggesting an EOQ of 1,440 units rather than the given 2,400 units.

Option D: 15 orders

Option C (15 orders) would result from incorrectly calculating 28,800 ÷ 1,920, suggesting an EOQ of 1,920 units rather than the given 2,400 units.

Memory Technique

Remember 'NADE' - Number of orders = Annual demand Divided by EOQ. Think 'Need A Delivery Every' time you reach the EOQ amount.

Reference Hint

Look up inventory management and Economic Order Quantity (EOQ) concepts in construction management or business administration chapters of contractor reference materials.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.