You need 2,400 linear feet of pipe delivered in equal quantities over 6 weeks. Your primary supplier can deliver 300 linear feet per week. How much additional supply capacity do you need per week?
Correct Answer
B) 100 linear feet
Weekly requirement: 2,400 ÷ 6 = 400 linear feet per week. Primary supplier provides 300 linear feet per week. Additional capacity needed: 400 - 300 = 100 linear feet per week.
Why This Is the Correct Answer
This is a straightforward supply chain capacity problem that requires calculating weekly demand and comparing it to existing supply capacity. First, we determine the weekly requirement by dividing total pipe needed (2,400 linear feet) by the delivery period (6 weeks), which equals 400 linear feet per week. Then we subtract the primary supplier's capacity (300 linear feet per week) from the weekly requirement to find the shortfall. The additional capacity needed is 400 - 300 = 100 linear feet per week.
Why the Other Options Are Wrong
Option C: 150 linear feet
50 linear feet is too low and represents only half of the actual shortfall needed to meet weekly requirements.
Option D: 200 linear feet
200 linear feet is significantly more than required and would result in receiving 500 linear feet per week instead of the needed 400.
Memory Technique
Remember 'DCS' - Demand minus Current supply equals Shortfall. Always calculate what you need first, then subtract what you have.
Reference Hint
Project Management chapter covering resource planning and supply chain management, or Construction Scheduling sections dealing with material delivery coordination.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
