EstatePass
Project MgmtBlueprintseasy17% of exam part

You discover a discrepancy between the architectural drawings and the structural drawings regarding beam locations. What should be your first course of action?

Correct Answer

A) Issue a Request for Information (RFI) to the design team

When discrepancies exist between drawings, the contractor should issue an RFI to the design team for clarification. This ensures proper coordination and prevents potential structural or design issues from proceeding without resolution.

Answer Options
A
Issue a Request for Information (RFI) to the design team
B
Make a field decision based on constructability
C
Follow the structural drawings as they are more technically specific
D
Follow the architectural drawings as they show the final design intent

Why This Is the Correct Answer

Issuing an RFI is the proper protocol when discrepancies exist between different drawing sets. This formal process ensures the design team addresses the conflict with a coordinated solution that maintains both architectural intent and structural integrity. Making assumptions or choosing one drawing over another without clarification could lead to costly errors, safety issues, or code violations that the contractor would be liable for.

Why the Other Options Are Wrong

Option B: Make a field decision based on constructability

Following only the architectural drawings ignores critical structural requirements and could compromise the building's safety and code compliance. Architectural drawings show design intent but may not reflect all structural constraints or load-bearing requirements.

Option C: Follow the structural drawings as they are more technically specific

Making unilateral field decisions on structural matters exceeds the contractor's authority and creates liability exposure. Beam locations affect structural integrity and must be resolved by qualified design professionals, not field personnel.

Option D: Follow the architectural drawings as they show the final design intent

While structural drawings are technically specific, following them without considering architectural intent could result in conflicts with the overall design, finishes, or spatial requirements. Both drawing sets must be coordinated.

Memory Technique

RFI = 'Resolve First, Install' - always resolve discrepancies before proceeding with installation

Reference Hint

AIA A201 General Conditions - Article 3.2 regarding contractor's review of contract documents and RFI procedures

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.