EstatePass
Business & FinanceRegulationsmedium15% of exam part

You are the general contractor on a project where a subcontractor has not been paid and threatens to file a lien. Under Florida Statute Chapter 713, what document should you request from the subcontractor before making final payment to avoid lien liability?

Correct Answer

A) Waiver of lien upon final payment

A waiver of lien upon final payment should be obtained before making final payment to protect against future lien claims. This document waives the right to file a lien for all work performed and materials supplied through the final payment date.

Answer Options
A
Waiver of lien upon final payment
B
Waiver of lien upon progress payment
C
Claim of lien
D
Notice to owner

Why This Is the Correct Answer

Under Florida Statute Chapter 713, a waiver of lien upon final payment is the appropriate document to request before making final payment to a subcontractor. This waiver protects the general contractor from future lien claims by having the subcontractor waive their right to file a lien for all work performed and materials supplied through the final payment date. It provides comprehensive protection against lien liability when the contractor-subcontractor relationship is concluding.

Why the Other Options Are Wrong

Option B: Waiver of lien upon progress payment

A waiver of lien upon progress payment is used for interim payments during the project, not for final payment. This type of waiver only covers work performed and materials supplied through a specific progress payment date, leaving potential exposure for subsequent work.

Option D: Notice to owner

A claim of lien is the actual lien document filed against the property when payment disputes occur. Requesting this would be counterproductive as it represents the very thing the contractor is trying to avoid.

Memory Technique

Think 'FINAL payment = FINAL waiver' - the waiver should match the payment stage to provide complete protection.

Reference Hint

Florida Statutes Chapter 713 - Mechanics' Liens, specifically sections dealing with lien waivers and releases

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.