EstatePass
Business & FinanceAdminmedium26% of exam part

You are preparing a payment application for a project that is 60% complete with a contract value of $500,000. Previous payments total $250,000, and 10% retainage is being held. What amount should be requested?

Correct Answer

D) $20,000

Total earned: $500,000 × 60% = $300,000. Less 10% retainage: $300,000 × 90% = $270,000. Less previous payments: $270,000 - $250,000 = $20,000.

Answer Options
A
$25,000
B
$30,000
C
$50,000
D
$20,000

Why This Is the Correct Answer

Option B is correct because it follows the proper payment application calculation sequence. First, calculate total earned to date ($500,000 × 60% = $300,000), then subtract retainage to get the amount available for payment ($300,000 × 90% = $270,000), and finally subtract previous payments to determine the current payment request ($270,000 - $250,000 = $20,000). This methodology ensures compliance with standard construction payment practices and contract terms.

Why the Other Options Are Wrong

Option A: $25,000

This amount represents 10% of the contract value without considering the proper calculation sequence of earned work, retainage deduction, and previous payments.

Option C: $50,000

This amount represents 6% of the contract value but fails to account for the proper sequence of calculating earned work minus retainage minus previous payments.

Memory Technique

Remember 'EPR': Earned work, minus Percentage retainage, minus Previous payments = current Request amount

Reference Hint

Chapter on Construction Contracts and Payment Procedures, specifically sections covering Progress Payments and Retainage

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.