EstatePass
Project MgmtConstructionmedium63% of exam part

You are managing a project where the formwork contractor wants to strip column forms after 12 hours in 70°F weather. What should be your decision?

Correct Answer

D) Wait until 24 hours minimum

Column forms typically require a minimum of 24 hours before stripping in normal temperature conditions to ensure adequate concrete strength development. 12 hours is insufficient for safe form removal.

Answer Options
A
Allow stripping as scheduled
B
Strip forms but leave shores in place
C
Require concrete strength testing first
D
Wait until 24 hours minimum

Why This Is the Correct Answer

Column forms require a minimum of 24 hours before stripping in normal temperature conditions (around 70°F) to ensure adequate concrete strength development for structural safety. The 12-hour timeframe proposed by the contractor is insufficient for the concrete to reach the necessary strength to support its own weight and any construction loads. Industry standards and building codes specify these minimum timeframes to prevent structural failure and ensure worker safety. Premature form removal can lead to concrete cracking, deformation, or collapse.

Why the Other Options Are Wrong

Option A: Allow stripping as scheduled

While concrete strength testing is good practice, the 12-hour timeframe is so clearly insufficient that testing is unnecessary - the minimum 24-hour requirement should be followed regardless.

Option B: Strip forms but leave shores in place

Shores are typically used for horizontal elements like slabs and beams, not vertical column forms, and 12 hours is still insufficient time regardless of shoring considerations.

Memory Technique

Use '24-7 Rule': 24 hours for vertical (columns), 7+ days for horizontal (slabs/beams) - like working 24/7 but for concrete curing times.

Reference Hint

ACI 318 Building Code Requirements for Structural Concrete, Chapter 6 - Formwork and Shoring, or Florida Building Code Chapter 19 - Concrete

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.