EstatePass
Project MgmtBlueprintshard17% of exam part

You are managing a project where the architect has issued Addendum #3 that changes the door schedule. The door supplier has already submitted shop drawings based on the original specifications. What should you do?

Correct Answer

A) Request revised shop drawings incorporating Addendum #3

All addenda must be incorporated into the work. The door supplier must revise their shop drawings to reflect the changes in Addendum #3 before approval and fabrication.

Answer Options
A
Request revised shop drawings incorporating Addendum #3
B
Proceed with the original shop drawings to avoid delays
C
Split the difference between old and new specifications
D
Install doors per original specs and modify later

Why This Is the Correct Answer

Addenda are legally binding modifications to the contract documents that supersede the original specifications. All work must comply with the most current contract documents, including all issued addenda. Shop drawings must accurately reflect the final specifications to ensure proper fabrication and installation. Proceeding with outdated shop drawings would result in non-compliant work that fails to meet contract requirements.

Why the Other Options Are Wrong

Option B: Proceed with the original shop drawings to avoid delays

This violates the fundamental principle that all addenda must be incorporated into the work. Using original shop drawings when addenda have modified the specifications would result in non-compliant installation and potential breach of contract.

Option C: Split the difference between old and new specifications

There is no 'splitting the difference' in construction contracts. The contract documents, including all addenda, must be followed exactly as written. Compromising between old and new specifications creates non-compliant work.

Option D: Install doors per original specs and modify later

Installing per original specifications when addenda have changed requirements violates the contract. Post-installation modifications are costly, time-consuming, and may not be technically feasible depending on the nature of the changes.

Memory Technique

Think 'ADD-enda means ADD to compliance' - you must always add/incorporate addenda changes into all work and submittals before proceeding.

Reference Hint

AIA A201 General Conditions - Section on Contract Documents and Modifications, or Florida Building Code Chapter 1 - Administration and Enforcement regarding contract document hierarchy

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.