EstatePass
Business & FinanceAdminhard26% of exam part

When processing a payment application, a contractor notices that 15% of the work claimed as complete is actually only 60% finished. If the application total is $200,000, what should the approved payment amount be?

Correct Answer

D) $188,000

15% of $200,000 = $30,000 claimed incorrectly. Actual completion: $30,000 × 0.60 = $18,000. Overstatement: $30,000 - $18,000 = $12,000. Approved amount: $200,000 - $12,000 = $188,000.

Answer Options
A
$170,000
B
$194,000
C
$182,000
D
$188,000

Why This Is the Correct Answer

Option C is correct because it properly calculates the overstatement in the payment application. When 15% of work ($30,000) is claimed as complete but is only 60% finished, the actual value is $18,000, creating a $12,000 overstatement. Subtracting this overstatement from the original application gives the correct approved amount of $188,000.

Why the Other Options Are Wrong

Option A: $170,000

This answer appears to use an incorrect calculation method, possibly subtracting 9% instead of calculating the actual overstatement based on the completion percentage.

Option C: $182,000

This answer incorrectly subtracts the full 15% ($30,000) from the application total, ignoring that 60% of that work was actually completed and should still be paid.

Memory Technique

Remember 'DAD': Disputed amount, Actual completion, Difference to subtract. This ensures you don't forget to account for the partially completed work.

Reference Hint

Florida Building Code Chapter 1, Section 109 - Fees and Permits, or AIA A201 General Conditions Article 9 - Payments and Completion

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.