When processing a payment application, a contractor notices that 15% of the work claimed as complete is actually only 60% finished. If the application total is $200,000, what should the approved payment amount be?
Correct Answer
D) $188,000
15% of $200,000 = $30,000 claimed incorrectly. Actual completion: $30,000 × 0.60 = $18,000. Overstatement: $30,000 - $18,000 = $12,000. Approved amount: $200,000 - $12,000 = $188,000.
Why This Is the Correct Answer
Option C is correct because it properly calculates the overstatement in the payment application. When 15% of work ($30,000) is claimed as complete but is only 60% finished, the actual value is $18,000, creating a $12,000 overstatement. Subtracting this overstatement from the original application gives the correct approved amount of $188,000.
Why the Other Options Are Wrong
Option A: $170,000
This answer appears to use an incorrect calculation method, possibly subtracting 9% instead of calculating the actual overstatement based on the completion percentage.
Option C: $182,000
This answer incorrectly subtracts the full 15% ($30,000) from the application total, ignoring that 60% of that work was actually completed and should still be paid.
Memory Technique
Remember 'DAD': Disputed amount, Actual completion, Difference to subtract. This ensures you don't forget to account for the partially completed work.
Reference Hint
Florida Building Code Chapter 1, Section 109 - Fees and Permits, or AIA A201 General Conditions Article 9 - Payments and Completion
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
