When installing composition shingle roofing in California seismic zones, what additional fastening requirement applies compared to standard installation?
Correct Answer
A) Use 6 nails per shingle instead of 4 in high seismic areas
California Building Code Section 1507.2.8.1 requires 6 fasteners per shingle in areas subject to high winds or seismic activity, compared to the standard 4 fasteners. This enhanced fastening pattern provides additional resistance to uplift forces during seismic events common in California.
Why This Is the Correct Answer
California Building Code Section 1507.2.8.1 requires 6 fasteners per shingle in areas subject to high winds or seismic activity, compared to the standard 4 fasteners. This enhanced fastening pattern provides additional resistance to uplift forces during seismic events common in California.
More trade-general-building Questions
When installing engineered lumber joists (I-joists) in California residential construction, what is the primary code requirement for web stiffeners?
What is the required attic ventilation ratio when a vapor retarder is installed on the warm-in-winter side of the ceiling according to the California Residential Code?
In California's Wildland-Urban Interface (WUI) areas, which underlayment requirement applies to Class A fire-rated roof assemblies?
In California, when installing a tankless water heater in a seismic zone, what additional requirement must be met beyond standard installation practices?
According to the California Building Code (CBC), what is the minimum lap splice length for #4 rebar in a concrete foundation wall in normal weight concrete with f'c = 3000 psi?
According to CBC requirements for retaining walls in California, what additional design consideration must be addressed for retaining walls over 4 feet in height located in seismic design categories D, E, and F?
When constructing retaining walls in California that exceed 4 feet in height, which CBC requirement must be met regarding drainage?
Under California regulations, when is a reduced pressure principle (RPP) backflow prevention assembly required for a residential water service connection?
Under California Title 24, what is the minimum electrical service size required for new single-family residential construction?
According to the California Building Code, buildings located in Seismic Design Category D must comply with which specific seismic design requirements?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
For concrete masonry unit (CMU) construction in California, what is the minimum grout space width required for vertical reinforcement according to the CBC?
Next Question
In California, which type of special inspection is required during the placement of reinforcing steel for cast-in-place concrete construction in Seismic Design Category D structures?