EstatePass
Business & FinanceRegulationsmedium15% of exam part

Under Florida Statutes Chapter 713, what is the maximum time limit for filing a claim of lien against real property for labor, services, or materials furnished?

Correct Answer

C) 90 days

Florida Statutes Chapter 713 requires that a claim of lien must be recorded within 90 days after the last day the lienor performed labor or services or furnished materials.

Answer Options
A
60 days
B
120 days
C
90 days
D
180 days

Why This Is the Correct Answer

Florida Statutes Chapter 713.13 specifically establishes that a claim of lien must be recorded within 90 days after the last day the lienor performed labor, furnished services, or delivered materials to the job site. This 90-day period is calculated from the final date of work or delivery, not from the contract date or project completion. The statute is very specific about this timeframe and failure to file within 90 days results in the complete loss of lien rights. This timing requirement is strictly enforced by Florida courts with no exceptions for delays.

Why the Other Options Are Wrong

Option A: 60 days

60 days is too short and not the statutory requirement under Chapter 713

Option D: 180 days

180 days is far beyond the statutory deadline and would result in complete loss of lien rights

Memory Technique

Think '90 days = 3 months' - roughly one business quarter to file your lien after final work completion

Reference Hint

Florida Statutes Chapter 713.13 - Construction Liens

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.