EstatePass
Business & FinanceRegulationsmedium15% of exam part

Under Florida Statute Chapter 713, what is the maximum time period a contractor has to file a construction lien after the last day of work or delivery of materials?

Correct Answer

A) 90 days

Florida Statute Chapter 713 requires that a construction lien must be filed within 90 days of the last day of work or delivery of materials to the job site. This is a strict deadline that cannot be extended.

Answer Options
A
90 days
B
60 days
C
120 days
D
45 days

Why This Is the Correct Answer

Florida Statute Chapter 713.13 specifically establishes that a lien claimant must record their claim of lien within 90 days after the final furnishing of labor, services, or materials by the lienor. This 90-day period is calculated from the last day the contractor performed work or delivered materials to the project site. The statute is very strict about this timeframe, and failure to file within this period results in the complete loss of lien rights with no possibility of extension or waiver.

Why the Other Options Are Wrong

Option B: 60 days

60 days is insufficient time under Florida law and would result in loss of lien rights if relied upon for filing deadlines.

Option C: 120 days

45 days is too short and does not align with Florida Statute Chapter 713 requirements for construction lien filing deadlines.

Memory Technique

Think '90 days = 3 months = one full season' - contractors have one full season (90 days) to file their lien after finishing work

Reference Hint

Florida Statutes Chapter 713.13 - Construction Liens, specifically the section on time limitations for recording claims of lien

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.