EstatePass
Project MgmtBlueprintsmedium17% of exam part

On an electrical schedule, a circuit is listed as '20A/1P/120V'. What does this designation indicate?

Correct Answer

B) 20 amp, 1 pole, 120 volt circuit

This designation indicates a 20 ampere, single pole, 120 volt circuit. The 'P' refers to poles on the circuit breaker, not phases. A single pole breaker controls one hot conductor.

Answer Options
A
20 amp, 1 pole, 120 watt circuit
B
20 amp, 1 pole, 120 volt circuit
C
20 amp, 1 phase, 120 watt circuit
D
20 amp, 1 phase, 120 volt circuit

Why This Is the Correct Answer

The designation '20A/1P/120V' stands for 20 amperes, 1 pole, and 120 volts. In electrical panel schedules, 'P' always refers to the number of poles on the circuit breaker — a single-pole breaker controls one hot conductor at 120V. This is the standard notation used by electricians and contractors when reading panel schedules and electrical drawings. Understanding this distinction is critical for verifying circuit capacity and breaker configuration before rough-in or service work.

Why the Other Options Are Wrong

Option A: 20 amp, 1 pole, 120 watt circuit

Option A incorrectly interprets 'P' as poles but substitutes 'watt' for 'volt.' Voltage (V) and wattage (W) are fundamentally different electrical quantities. Voltage is the potential difference driving current, while wattage is power (V × A). Circuit designations specify voltage, not wattage.

Option C: 20 amp, 1 phase, 120 watt circuit

Option C misreads 'P' as 'phase' instead of 'pole' and also incorrectly substitutes watts for volts. Single-phase circuits are described differently in specifications. 'P' on a breaker schedule always denotes poles, not phase count.

Option D: 20 amp, 1 phase, 120 volt circuit

Option D correctly identifies 120V but misreads '1P' as '1 phase' rather than '1 pole.' While single-pole breakers do operate on single-phase power, the 'P' in panel schedule notation specifically refers to the number of poles on the breaker, not the phase configuration of the supply.

Memory Technique

Remember 'P is for Pole, not Phase' — the breaker has poles, the system has phases. On a schedule, P always counts the breaker poles.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.