On a grading plan, if the existing grade is 98.5' and the proposed grade is 101.2', how much fill is required at this location?
Correct Answer
C) 2.7 feet of fill
Fill is required when the proposed grade is higher than existing grade. 101.2' - 98.5' = 2.7 feet of fill needed at this location.
Why This Is the Correct Answer
When the proposed grade (101.2') is higher than the existing grade (98.5'), material must be added to raise the ground level, which is called fill. The calculation is straightforward: proposed grade minus existing grade equals the amount of fill needed. Since 101.2' - 98.5' = 2.7', this location requires 2.7 feet of fill material to achieve the desired grade.
Why the Other Options Are Wrong
Option A: 2.7 feet of cut
This option incorrectly identifies the operation as 'cut' when the proposed grade is higher than existing grade, which requires fill, not cut.
Option B: 1.7 feet of fill
This option incorrectly identifies the operation as 'cut' when fill is needed, and also uses the wrong calculation result of 1.7 feet instead of 2.7 feet.
Memory Technique
Use 'FILL UP' - when proposed grade goes UP from existing grade, you need to FILL. For the math: 'Proposed minus Past (existing) = Project requirement.'
Reference Hint
Look up site work and grading specifications in Division 31 of construction specifications, or earthwork sections in construction reference materials.
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass