In material procurement, what is the primary purpose of expediting?
Correct Answer
B) To monitor and accelerate delivery schedules
Expediting is the process of monitoring supplier progress and taking action to accelerate delivery when materials are behind schedule. It focuses on schedule compliance rather than cost or quality.
Why This Is the Correct Answer
Expediting is specifically defined as the process of monitoring and accelerating delivery schedules to ensure materials arrive on time. The primary function of expediting is to track supplier progress and take corrective action when deliveries fall behind schedule. This process is critical for maintaining project timelines and avoiding costly delays. Expediting focuses exclusively on schedule compliance and delivery timing rather than cost negotiations or quality control.
Why the Other Options Are Wrong
Option A: To negotiate better prices with suppliers
Transportation cost reduction is typically addressed through logistics planning, carrier selection, and shipping optimization. Expediting may sometimes involve upgrading shipping methods to meet deadlines, but this is secondary to its primary schedule monitoring function.
Option C: To reduce transportation costs
Price negotiation is a separate procurement function typically handled during the bidding or contract award phase. While expediting may involve discussions with suppliers, its primary focus is schedule compliance, not cost reduction or price negotiations.
Option D: To ensure materials meet quality specifications
Quality assurance and specification compliance are handled through inspection, testing, and quality control processes. While expediting may coordinate with quality teams, its primary function is schedule monitoring and acceleration, not quality verification.
Memory Technique
EXPEDiting = EXPEDite delivery - both words share the same root meaning 'to speed up' or 'make faster'
Reference Hint
Look up 'Material Procurement and Expediting' in construction management chapters or 'Project Scheduling and Material Management' sections
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?