EstatePass
Business & FinanceOperationseasy10% of exam part

In Critical Path Method (CPM) scheduling, what is the float or slack time for activities on the critical path?

Correct Answer

A) Zero

Activities on the critical path have zero float or slack time, meaning any delay in these activities will directly delay the project completion date. This is the defining characteristic of the critical path.

Answer Options
A
Zero
B
Calculated as late start minus early start
C
Equal to the project duration
D
One day

Why This Is the Correct Answer

Activities on the critical path have zero float or slack time by definition. The critical path represents the longest sequence of activities through a project network, and any delay in these activities will directly extend the project completion date. Float time is calculated as Late Start - Early Start (or Late Finish - Early Finish), and for critical path activities, these values are equal, resulting in zero float. This zero float characteristic is what makes the critical path 'critical' to project timing.

Why the Other Options Are Wrong

Option B: Calculated as late start minus early start

One day is incorrect because float time is not a fixed value but depends on the specific activity and project schedule. Non-critical activities may have varying amounts of float time (could be days, weeks, or months), but critical path activities specifically have zero float, not one day.

Option C: Equal to the project duration

While the formula 'late start minus early start' is correct for calculating float time, this option doesn't answer what the float actually IS for critical path activities. The calculation method is right, but when applied to critical path activities, late start equals early start, making the result zero.

Option D: One day

Float time being equal to project duration is incorrect because this would mean an activity could be delayed by the entire project length without affecting completion, which is impossible. Float represents available delay time for individual activities, not the total project timeframe.

Memory Technique

CRITICAL PATH = ZERO SLACK. Think 'Critical means no wiggle room' - just like a critical patient has zero time to waste, critical path activities have zero float time.

Reference Hint

Project Management/Scheduling chapter, specifically CPM (Critical Path Method) section covering float calculations and critical path characteristics

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.