In CPM scheduling, which relationship type is most commonly used and represents a finish-to-start dependency?

Correct Answer

D) FS (Finish-to-Start)

Finish-to-Start (FS) is the most common dependency relationship in CPM scheduling, where one activity must finish before the successor activity can start. This represents the typical sequential workflow in construction.

Answer Options
A
FF (Finish-to-Finish)
B
SF (Start-to-Finish)
C
SS (Start-to-Start)
D
FS (Finish-to-Start)

Why This Is the Correct Answer

Finish-to-Start (FS) is indeed the most commonly used dependency relationship in CPM scheduling, representing approximately 80-90% of all project relationships. This relationship type reflects the natural sequential flow of construction activities where one task must be completed before the next can begin. For example, concrete must be poured and cured before framing can start, or electrical rough-in must be finished before drywall installation can commence. This logical progression makes FS the default and most intuitive relationship type in construction project management.

Why the Other Options Are Wrong

Option B: SF (Start-to-Finish)

Start-to-Finish (SF) is the rarest dependency type in construction scheduling and is seldom used in practice. This relationship means an activity cannot finish until another activity starts, which goes against typical construction logic and workflow patterns.

Option C: SS (Start-to-Start)

Finish-to-Finish (FF) relationships are the least common type, used when two activities must finish around the same time or one activity's completion depends on another's completion. An example would be final cleanup finishing when final inspection is completed, but this represents a small percentage of construction relationships.

Memory Technique

Remember 'FS First' - Finish-to-Start is First in frequency. Also think 'Finish before Start' as the natural construction flow: finish the foundation before starting the framing, finish framing before starting roofing.

Reference Hint

Look up CPM scheduling fundamentals in Chapter 6 (Project Scheduling) of construction management references, or the scheduling section of project management guides that cover the four dependency types and their applications.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.