EstatePass
Business & FinanceOperationsmedium10% of exam part

In CPM scheduling, what does it mean when an activity has negative float?

Correct Answer

C) The activity is behind schedule and will delay the project

Negative float indicates that an activity is behind schedule and will cause the overall project to be delayed beyond its planned completion date. This requires immediate attention to get the project back on track.

Answer Options
A
The activity can be delayed without affecting the project
B
The activity is ahead of schedule
C
The activity is behind schedule and will delay the project
D
The activity is on the critical path

Why This Is the Correct Answer

CORRECT_ANSWER - Negative float occurs when an activity's late finish date is earlier than its early finish date, meaning the activity is taking longer than originally planned. This creates a deficit in the schedule that pushes the project completion date beyond the target date. Negative float is a red flag that requires immediate corrective action, such as crashing or fast-tracking, to bring the project back on schedule.

Why the Other Options Are Wrong

Option A: The activity can be delayed without affecting the project

While activities with negative float may be on the critical path, simply being on the critical path doesn't create negative float. Critical path activities have zero float when on schedule. Negative float specifically indicates the activity is behind schedule, not just critical.

Option B: The activity is ahead of schedule

This describes positive float, which is the opposite of negative float. Activities that can be delayed without affecting the project have slack time or positive float. Negative float means any further delay will definitely impact the project completion date.

Memory Technique

Think 'Negative = Need help!' - negative float means the project needs immediate help to get back on track, just like a negative bank balance needs immediate attention.

Reference Hint

Look up CPM scheduling and float calculations in the project management or scheduling chapter of your contractor reference manual, typically found in the project planning section.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.