In CPM scheduling, if Activity X has an Early Start of Day 10, Duration of 4 days, and Late Finish of Day 18, what is the float time for this activity?
Correct Answer
D) 4 days
Float = Late Finish - Early Start - Duration = 18 - 10 - 4 = 4 days. This means Activity X can be delayed up to 4 days without affecting the project completion date.
Why This Is the Correct Answer
Float time represents the amount of time an activity can be delayed without affecting the project's critical path or completion date. The standard CPM formula for calculating float is: Float = Late Finish - Early Start - Duration. Using the given values: Float = 18 - 10 - 4 = 4 days. This means Activity X has 4 days of scheduling flexibility before it impacts other activities or the project timeline.
Why the Other Options Are Wrong
Option A: 6 days
This answer of 2 days would result from an incorrect calculation, possibly confusing the formula or subtracting values in the wrong order.
Option B: 8 days
This answer of 8 days comes from only calculating Late Finish minus Early Start (18-10=8) while forgetting to subtract the activity duration from the formula.
Option C: 2 days
This answer of 6 days might result from incorrectly calculating Late Finish minus Early Start (18-10=8) and then subtracting 2 instead of the full duration of 4 days.
Memory Technique
Remember 'FLEDs' - Float = Late Finish - Early Start - Duration. Think 'activities that have FLED the critical path have float time.'
Reference Hint
Look up CPM scheduling methods and float calculations in the Project Management or Scheduling chapter of your contractor reference manual.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
