In a detail drawing showing a wall section, what does the designation '2/A-3' typically refer to?

Correct Answer

D) Detail number 2 on sheet A-3

The notation '2/A-3' indicates detail number 2 found on sheet A-3. This is the standard format for referencing details in construction drawings.

Answer Options
A
Scale of 2 inches equals A-3 feet
B
Second revision of detail A-3
C
Zone 2 of grid line A-3
D
Detail number 2 on sheet A-3

Why This Is the Correct Answer

The notation '2/A-3' follows the standard architectural drawing convention where the number before the slash indicates the detail number, and the designation after the slash indicates the sheet where that detail can be found. In this case, detail number 2 is located on sheet A-3. This referencing system allows architects and contractors to quickly locate specific details throughout the drawing set by providing both the detail identifier and its sheet location.

Why the Other Options Are Wrong

Option A: Scale of 2 inches equals A-3 feet

This misinterprets the notation as a scale indicator. Drawing scales are expressed differently, such as '1/4"=1'-0"' or '1:50'. The slash in '2/A-3' is not indicating a mathematical relationship between measurements but rather separating the detail number from the sheet reference.

Option B: Second revision of detail A-3

This confuses detail references with grid line systems. Grid lines are typically labeled with letters and numbers (like A-3) and shown on floor plans, but the '2/' prefix indicates this is a detail callout, not a grid zone reference. Grid references don't use the number/letter format shown here.

Memory Technique

Remember 'Detail/Sheet' - the number before the slash is the Detail number, the designation after is the Sheet location. Think 'D/S' for Detail/Sheet.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.