In a CPM schedule, Activity A has a duration of 5 days, Activity B has a duration of 8 days, and Activity C has a duration of 3 days. If A and B can start simultaneously, and C cannot start until both A and B are complete, what is the total project duration?
Correct Answer
B) 11 days
Since A (5 days) and B (8 days) run concurrently, B finishes last at day 8. Activity C (3 days) starts after B completes, so total duration is 8 + 3 = 11 days.
Why This Is the Correct Answer
In CPM scheduling, when activities run concurrently, the longest duration determines when both are complete. Activities A (5 days) and B (8 days) start simultaneously, so B finishes last at day 8. Activity C cannot begin until both A and B are finished, so C starts on day 8 and runs for 3 days. The total project duration is therefore 8 + 3 = 11 days.
Why the Other Options Are Wrong
Option A: 8 days
This incorrectly adds all three activity durations (5+8+3=16) then subtracts 3, or assumes C starts after A finishes (5+8=13). This ignores that A and B run concurrently.
Option C: 13 days
This only accounts for the duration of Activity B (8 days) and completely ignores Activity C, which must still be completed after both A and B finish.
Memory Technique
Remember 'Concurrent = Controlling': when activities run at the same time, the longest one controls when the next phase can start. Think of it as waiting for the slowest person in your group.
Reference Hint
Look up CPM (Critical Path Method) scheduling in construction management chapters, specifically sections on concurrent activities and project duration calculations.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
