EstatePass
Business & FinanceOperationsmedium10% of exam part

In a CPM network, Activity X has an early start of day 15, duration of 8 days, and late finish of day 28. What is the total float for this activity?

Correct Answer

A) 5 days

Early finish = Early start + Duration = 15 + 8 = 23. Total float = Late finish - Early finish = 28 - 23 = 5 days. This represents how long the activity can be delayed without affecting project completion.

Answer Options
A
5 days
B
7 days
C
3 days
D
10 days

Why This Is the Correct Answer

Option B is correct because total float is calculated by finding the difference between late finish and early finish. First, we calculate the early finish: Early Start (15) + Duration (8) = 23 days. Then we find the total float: Late Finish (28) - Early Finish (23) = 5 days. This means Activity X can be delayed up to 5 days without impacting the overall project completion date.

Why the Other Options Are Wrong

Option B: 7 days

Option D (10 days) is incorrect because it appears to be simply subtracting Duration from Late Finish (28 - 8 = 20, not 10) or possibly calculating Late Start minus Early Start incorrectly.

Option C: 3 days

Option A (3 days) is incorrect because it appears to be calculating Late Finish minus Early Start minus Duration (28 - 15 - 8 = 5, not 3), or possibly confusing this with a different float calculation method.

Memory Technique

Remember 'FLED' - Float = Late finish minus Early finish Duration. Or think 'How much can I be LATE?' = Late Finish - Early Finish.

Reference Hint

Look up 'Critical Path Method (CPM)' and 'Float Calculations' in your project management or scheduling chapter, typically found in construction management sections.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.