In a CPM network, Activity X has an early start of day 15, duration of 8 days, and late finish of day 28. What is the total float for this activity?
Correct Answer
A) 5 days
Early finish = Early start + Duration = 15 + 8 = 23. Total float = Late finish - Early finish = 28 - 23 = 5 days. This represents how long the activity can be delayed without affecting project completion.
Why This Is the Correct Answer
Option B is correct because total float is calculated by finding the difference between late finish and early finish. First, we calculate the early finish: Early Start (15) + Duration (8) = 23 days. Then we find the total float: Late Finish (28) - Early Finish (23) = 5 days. This means Activity X can be delayed up to 5 days without impacting the overall project completion date.
Why the Other Options Are Wrong
Option B: 7 days
Option D (10 days) is incorrect because it appears to be simply subtracting Duration from Late Finish (28 - 8 = 20, not 10) or possibly calculating Late Start minus Early Start incorrectly.
Option C: 3 days
Option A (3 days) is incorrect because it appears to be calculating Late Finish minus Early Start minus Duration (28 - 15 - 8 = 5, not 3), or possibly confusing this with a different float calculation method.
Memory Technique
Remember 'FLED' - Float = Late finish minus Early finish Duration. Or think 'How much can I be LATE?' = Late Finish - Early Finish.
Reference Hint
Look up 'Critical Path Method (CPM)' and 'Float Calculations' in your project management or scheduling chapter, typically found in construction management sections.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
