In a CPM network, Activity X has an Early Start of day 15, Duration of 6 days, and Late Finish of day 25. What is the Late Start for this activity?

Correct Answer

C) Day 19

Late Start is calculated as Late Finish minus Duration. Late Start = 25 - 6 = 19. This represents the latest day the activity can start without delaying the project.

Answer Options
A
Day 15
B
Day 21
C
Day 19
D
Day 25

Why This Is the Correct Answer

Option B is correct because Late Start is calculated using the fundamental CPM formula: Late Start = Late Finish - Duration. Given that the Late Finish is day 25 and the Duration is 6 days, the Late Start equals 25 - 6 = 19. This represents the latest possible day Activity X can begin without causing the project to be delayed beyond its scheduled completion date.

Why the Other Options Are Wrong

Option A: Day 15

Day 21 would be the Early Finish (Early Start + Duration = 15 + 6 = 21), not the Late Start. This represents when the activity would finish if started at its earliest possible time.

Option B: Day 21

Day 25 is the Late Finish, not the Late Start. This represents the latest day the activity must be completed, not when it can start.

Memory Technique

Remember 'LF - D = LS' (Late Finish minus Duration equals Late Start). Think of it as working backwards: if you must finish by day 25 and need 6 days to complete the work, you must start by day 19 at the latest.

Reference Hint

Look up CPM (Critical Path Method) calculations in the Project Management or Scheduling chapter of your contractor reference manual, specifically the section on backward pass calculations.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.