For wood frame construction in California Seismic Design Category D, what is the maximum spacing for anchor bolts along the sill plate?

Correct Answer

B) 6 feet on center

CBC Section 2308.3.1 specifies that anchor bolts must be placed at maximum 6-foot intervals in Seismic Design Category D. Additionally, bolts must be located within 12 inches of each end of each sill plate. This closer spacing compared to lower seismic zones ensures adequate transfer of lateral forces from the structure to the foundation.

Answer Options
A
8 feet on center
B
6 feet on center
C
4 feet on center
D
12 feet on center

Why This Is the Correct Answer

Option B (6 feet on center) is correct per CBC Section 2308.3.1. In SDC D, anchor bolts must be spaced no more than 6 feet apart along the sill plate to ensure adequate transfer of lateral seismic forces from the wood frame structure to the concrete foundation. The code also requires bolts within 12 inches of each plate end.

Why the Other Options Are Wrong

Option A: 8 feet on center

Option A (8 feet on center) is incorrect. An 8-foot spacing may apply in lower seismic zones or under other codes, but CBC SDC D requires tighter 6-foot spacing. Larger spacing reduces the number of connection points, which is insufficient for high-seismic force transfer.

Option C: 4 feet on center

Option C (4 feet on center) is incorrect as a maximum β€” this spacing is more conservative than required and would be structurally acceptable, but it does not represent the code maximum. The CBC allows up to 6-foot spacing; 4 feet is tighter than necessary.

Option D: 12 feet on center

Option D (12 feet on center) is far too loose. A 12-foot bolt spacing would leave long stretches of sill plate unanchored, creating a critical failure point during seismic events when lateral forces attempt to slide the wood frame off the foundation.

Memory Technique

Remember: '6 feet for SDC D sill anchors.' Visualize a 6-foot ruler lying along the sill plate β€” every time you reach the end of the ruler, you must have an anchor bolt. The '12-inch from the end' rule is a separate bonus requirement to anchor plate ends.

Was this explanation helpful?

More trade-general-building Questions

When installing engineered lumber joists (I-joists) in California residential construction, what is the primary code requirement for web stiffeners?

What is the required attic ventilation ratio when a vapor retarder is installed on the warm-in-winter side of the ceiling according to the California Residential Code?

In California's Wildland-Urban Interface (WUI) areas, which underlayment requirement applies to Class A fire-rated roof assemblies?

In California, when installing a tankless water heater in a seismic zone, what additional requirement must be met beyond standard installation practices?

According to the California Building Code (CBC), what is the minimum lap splice length for #4 rebar in a concrete foundation wall in normal weight concrete with f'c = 3000 psi?

According to CBC requirements for retaining walls in California, what additional design consideration must be addressed for retaining walls over 4 feet in height located in seismic design categories D, E, and F?

When constructing retaining walls in California that exceed 4 feet in height, which CBC requirement must be met regarding drainage?

Under California regulations, when is a reduced pressure principle (RPP) backflow prevention assembly required for a residential water service connection?

Under California Title 24, what is the minimum electrical service size required for new single-family residential construction?

According to the California Building Code, buildings located in Seismic Design Category D must comply with which specific seismic design requirements?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.