EstatePass
Project MgmtBlueprintshard17% of exam part

During plan review, a contractor notices that the fire-rated wall assembly specified in Division 09 conflicts with the fire rating shown on the architectural floor plan. The specification calls for a 2-hour rating while the floor plan shows 1-hour. What action should be taken?

Correct Answer

A) Submit an RFI to resolve the conflict before proceeding

Any conflict between drawings and specifications must be resolved through proper channels (RFI) before construction proceeds. Fire ratings are critical safety issues that require accurate resolution.

Answer Options
A
Submit an RFI to resolve the conflict before proceeding
B
Use whichever rating is less expensive to construct
C
Use the 2-hour rating since specifications take precedence
D
Use the 1-hour rating since the floor plan is more current

Why This Is the Correct Answer

When there are conflicts between contract documents (drawings vs. specifications), the contractor must never assume which document takes precedence or make independent decisions about critical safety systems. Fire ratings are life safety issues that must be precisely correct according to code requirements. An RFI (Request for Information) is the proper contractual procedure to get clarification from the design team before proceeding with construction. This protects the contractor from liability and ensures the building meets all safety requirements.

Why the Other Options Are Wrong

Option B: Use whichever rating is less expensive to construct

While specifications often take precedence over drawings in many contracts, this is not universal and should never be assumed. Fire rating conflicts require definitive clarification, not assumptions about document hierarchy.

Option C: Use the 2-hour rating since specifications take precedence

Assuming the floor plan is more current is dangerous speculation without verification. Contract documents don't automatically have precedence based on perceived currency, and fire ratings are too critical for assumptions.

Option D: Use the 1-hour rating since the floor plan is more current

Cost should never be the determining factor for fire safety systems. Fire ratings are code-mandated safety requirements that must meet specific performance criteria regardless of construction cost.

Memory Technique

RFI = 'Resolve Fire Issues' - whenever you see conflicts in fire ratings, think RFI immediately

Reference Hint

Florida Building Code Chapter 7 (Fire and Smoke Protection Features) and AIA A201 General Conditions regarding conflicts in contract documents

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.