During contract administration, a change order increases the project scope by $15,000. The original contract included a 15% markup on change orders. What is the total amount to be added to the contract?
Correct Answer
C) $17,250
The change order amount includes the base cost plus markup: $15,000 + ($15,000 × 0.15) = $15,000 + $2,250 = $17,250. This covers both the direct costs and the contractor's overhead and profit on the additional work.
Why This Is the Correct Answer
Option B correctly applies the 15% markup to the base change order amount. When a contract specifies a markup percentage on change orders, this percentage must be applied to the base cost to determine the total contract addition. The calculation is straightforward: base cost ($15,000) plus markup ($15,000 × 0.15 = $2,250) equals $17,250 total. This markup covers the contractor's overhead and profit on the additional work scope.
Why the Other Options Are Wrong
Option B: $16,500
Option C of $16,500 represents only a 10% markup ($15,000 + $1,500), which is incorrect since the contract specifically states a 15% markup.
Option D: $15,000
Option D of $18,750 represents a 25% markup ($15,000 + $3,750), which exceeds the contractually agreed upon 15% markup rate.
Memory Technique
Remember 'Base + Bonus' - the base cost plus the bonus (markup) equals the total contract addition
Reference Hint
Florida Building Code - Administrative Chapter 1, Section on Contract Administration and Change Orders
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
