EstatePass
Business & FinanceAdmineasy26% of exam part

During contract administration, a change order increases the project scope by $15,000. The original contract included a 15% markup on change orders. What is the total amount to be added to the contract?

Correct Answer

C) $17,250

The change order amount includes the base cost plus markup: $15,000 + ($15,000 × 0.15) = $15,000 + $2,250 = $17,250. This covers both the direct costs and the contractor's overhead and profit on the additional work.

Answer Options
A
$18,750
B
$16,500
C
$17,250
D
$15,000

Why This Is the Correct Answer

Option B correctly applies the 15% markup to the base change order amount. When a contract specifies a markup percentage on change orders, this percentage must be applied to the base cost to determine the total contract addition. The calculation is straightforward: base cost ($15,000) plus markup ($15,000 × 0.15 = $2,250) equals $17,250 total. This markup covers the contractor's overhead and profit on the additional work scope.

Why the Other Options Are Wrong

Option B: $16,500

Option C of $16,500 represents only a 10% markup ($15,000 + $1,500), which is incorrect since the contract specifically states a 15% markup.

Option D: $15,000

Option D of $18,750 represents a 25% markup ($15,000 + $3,750), which exceeds the contractually agreed upon 15% markup rate.

Memory Technique

Remember 'Base + Bonus' - the base cost plus the bonus (markup) equals the total contract addition

Reference Hint

Florida Building Code - Administrative Chapter 1, Section on Contract Administration and Change Orders

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.