During a project, the owner requests additional work that was not included in the original contract. What is the contractor's first step in the change order process?
Correct Answer
B) Document the request in writing and obtain written authorization before proceeding
All change requests must be documented in writing and receive written authorization before work begins. This protects both parties and ensures proper payment for additional work performed.
Why This Is the Correct Answer
Option B is correct because proper change order procedures require written documentation and authorization before any additional work begins. This protects both the contractor and owner by establishing clear scope, cost, and timeline changes. Written authorization ensures the contractor will be paid for the additional work and prevents disputes later. Florida construction law and standard industry practices mandate this documentation process.
Why the Other Options Are Wrong
Option A: Estimate the cost and add it to the next payment application
Estimating costs and adding to payment applications without proper written authorization puts the contractor at risk of non-payment. The owner could dispute the charges since they never formally agreed to the additional work or costs.
Option C: Begin the work immediately to avoid project delays
Refusing additional work unless a completely new contract is executed is unnecessarily rigid and impractical. Change orders are the standard industry mechanism for handling additional work within existing contracts.
Option D: Refuse the work unless a new contract is executed
Beginning work immediately without written authorization is dangerous and can lead to non-payment disputes. The contractor may perform work that the owner later refuses to pay for, creating financial loss and legal complications.
Memory Technique
Use the acronym 'DRAW' - Document, Request authorization, Approve in writing, then Work can begin
Reference Hint
Florida Building Code Chapter 1, Section 105 - Construction Documents and Change Orders; also check contract administration sections in construction management references
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
