EstatePass
Business & FinanceOperationsmedium10% of exam part

During a project review, you discover that material deliveries are consistently arriving 5 days early, causing storage problems and increased handling costs. What inventory management strategy should be implemented?

Correct Answer

C) Negotiate with suppliers to adjust delivery schedules to match project needs

Early deliveries increase carrying costs and storage problems. The best solution is to work with suppliers to align delivery schedules with actual project needs, implementing better coordination rather than accepting inefficient practices.

Answer Options
A
Accept the early deliveries to ensure material availability
B
Increase safety stock levels to accommodate early deliveries
C
Negotiate with suppliers to adjust delivery schedules to match project needs
D
Find additional storage space to handle the early deliveries

Why This Is the Correct Answer

Negotiating with suppliers to adjust delivery schedules addresses the root cause of the problem. This approach eliminates unnecessary storage costs, reduces material handling, minimizes risk of damage or theft, and optimizes cash flow by aligning material arrivals with actual construction needs. It's a proactive solution that improves overall project efficiency and cost control rather than simply accommodating inefficient practices.

Why the Other Options Are Wrong

Option A: Accept the early deliveries to ensure material availability

Accepting early deliveries perpetuates the problem and increases project costs through unnecessary storage, handling, and potential material damage or theft. This reactive approach fails to address the inefficiency and wastes resources that could be better utilized elsewhere in the project.

Option B: Increase safety stock levels to accommodate early deliveries

Increasing safety stock levels would worsen the storage problem and further increase carrying costs. This approach compounds the issue by requiring even more storage space and capital tied up in inventory, rather than solving the timing mismatch problem.

Option D: Find additional storage space to handle the early deliveries

Finding additional storage space treats the symptom rather than the cause, adding unnecessary rental or construction costs. This solution doesn't eliminate the inefficiency and may encourage continued poor delivery timing, creating ongoing operational problems and increased project expenses.

Memory Technique

Remember 'SYNC' - Suppliers should be Synchronized with Your Needs and Construction schedule. Don't store early, negotiate to align delivery timing with actual project requirements.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.