During a project review, you discover that Activity A (5 days) and Activity B (8 days) can be performed concurrently instead of sequentially as originally planned. What time savings will this create?
Correct Answer
D) 5 days
When activities are performed sequentially, total time is 5 + 8 = 13 days. When performed concurrently, total time is 8 days (the longer of the two activities). Time savings = 13 - 8 = 5 days.
Why This Is the Correct Answer
When activities change from sequential to concurrent execution, the time savings equals the original sequential duration minus the new concurrent duration. Sequential execution requires 5 + 8 = 13 days total. Concurrent execution only requires 8 days (the duration of the longest activity). The time savings is therefore 13 - 8 = 5 days.
Why the Other Options Are Wrong
Option A: 13 days
3 days represents only the difference between the two activity durations (8-5=3), but this doesn't account for the actual time savings achieved by running them concurrently instead of sequentially.
Option C: 3 days
8 days is the duration of the longer activity and represents the new project duration when activities run concurrently, but it's not the time savings amount.
Memory Technique
Think 'SAVE = Sequential - Actual concurrent duration' where the actual concurrent duration is always the longest single activity when tasks overlap completely.
Reference Hint
Project Management chapter covering Critical Path Method (CPM) and activity scheduling techniques
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
