EstatePass
Project MgmtConstructionmedium63% of exam part

During a cut and fill operation, the contractor discovers that the cut material has a swell factor of 25%. If 1,000 cubic yards of material needs to be removed in-place, how many cubic yards of hauling capacity will be required?

Correct Answer

B) 1,250 cubic yards

With a 25% swell factor, the material expands when excavated. 1,000 cubic yards × 1.25 = 1,250 cubic yards of loose material to haul.

Answer Options
A
1,500 cubic yards
B
1,250 cubic yards
C
1,000 cubic yards
D
800 cubic yards

Why This Is the Correct Answer

When soil is excavated from its natural state, it expands due to the loosening of particles and introduction of air voids. A 25% swell factor means the material increases in volume by 25% when disturbed. To calculate hauling capacity, you multiply the in-place volume by (1 + swell factor percentage): 1,000 × 1.25 = 1,250 cubic yards. This represents the actual loose volume that trucks must transport.

Why the Other Options Are Wrong

Option C: 1,000 cubic yards

1,000 cubic yards is the in-place volume before excavation. This ignores the swell factor entirely and would result in insufficient hauling capacity.

Option D: 800 cubic yards

800 cubic yards represents a 20% shrinkage (1,000 × 0.8), which would be the compacted volume, not the loose hauling volume. This confuses shrinkage with swell.

Memory Technique

Think 'SWELL = SELL more trucks' - when soil swells, you need to SELL (buy/rent) more hauling capacity than the original in-place volume.

Reference Hint

Look up 'Earthwork and Excavation' or 'Soil Volume Changes' in construction management references, typically found in site work or excavation chapters.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.