EstatePass
Project MgmtBlueprintseasy17% of exam part

An electrical schedule shows a 200-amp panel with a demand factor of 75%. What is the calculated electrical demand for this panel?

Correct Answer

C) 150 amps

The electrical demand is calculated by multiplying the panel rating by the demand factor: 200 amps × 0.75 = 150 amps demand.

Answer Options
A
125 amps
B
175 amps
C
150 amps
D
200 amps

Why This Is the Correct Answer

The electrical demand is calculated by applying the demand factor to the panel's rated capacity. When a 200-amp panel has a 75% demand factor, you multiply 200 amps × 0.75 to get 150 amps. This represents the actual expected electrical load on the panel, which is typically less than the full rated capacity due to the fact that not all circuits operate at maximum load simultaneously.

Why the Other Options Are Wrong

Option B: 175 amps

125 amps would result from incorrectly using a 62.5% demand factor (200 × 0.625 = 125), which is not the given demand factor of 75%.

Option D: 200 amps

200 amps represents the full panel rating without applying any demand factor, which ignores the given 75% demand factor requirement.

Memory Technique

Remember 'Demand = Rating × Factor' - think of it as 'what you actually need (demand) equals what's available (rating) times how much you'll really use (factor)'

Reference Hint

Florida Building Code, Chapter 22 (Electrical) or NEC Article 220 (Branch-Circuit, Feeder, and Service Load Calculations)

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.