EstatePass
Business & FinanceAdminmedium26% of exam part

According to Florida construction lien law, what is the maximum time period for filing a claim of lien after the last day of work?

Correct Answer

D) 90 days

Florida Statute 713.13 requires that a claim of lien be filed within 90 days of the last day the lienor performed work or furnished materials to the property.

Answer Options
A
120 days
B
60 days
C
45 days
D
90 days

Why This Is the Correct Answer

Florida Statute 713.13 specifically establishes a 90-day deadline for filing a claim of lien after the last day of work or material delivery. This 90-day period is a strict statutory requirement that cannot be extended or waived. The statute is designed to provide a reasonable timeframe for contractors and suppliers to perfect their lien rights while also providing property owners with certainty about potential claims. Missing this 90-day deadline results in the complete loss of lien rights, making it one of the most critical deadlines in Florida construction law.

Why the Other Options Are Wrong

Option A: 120 days

120 days exceeds the statutory deadline and would result in an invalid lien

Option B: 60 days

45 days is too short and not the statutory requirement under Florida law

Memory Technique

Think '90 days to save the day' - you have exactly 90 days from your last day of work to file your lien or lose your rights forever

Reference Hint

Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.13

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.