According to California regulations, when a qualifying individual for a contractor's license dies, becomes disabled, or severs employment, how long does the contractor have to replace the qualifier before the license becomes invalid?
Correct Answer
C) 90 days
Business and Professions Code Section 7068.1 provides that when a qualifying individual dies, becomes disabled, or severs employment with the licensed entity, the contractor has 90 days to replace the qualifier. Failure to do so within this timeframe results in automatic suspension of the license until a replacement qualifier is approved.
Why This Is the Correct Answer
B&P Code Section 7068.1 grants the licensed contractor exactly 90 days to replace a qualifying individual who has died, become disabled, or severed their employment relationship. During this 90-day window, the contractor may continue operating. If no replacement qualifier is approved within 90 days, the license automatically suspends until a new qualifier is in place.
Why the Other Options Are Wrong
Option A: 120 days
120 days is not the grace period provided under Section 7068.1. This figure exceeds the statutory timeframe and could lead a contractor to believe they have more time than the law allows, potentially resulting in license suspension if they rely on this incorrect period.
Option B: 30 days
30 days is far too short and does not match the statutory grace period. While 30 days might seem like a reasonable administrative deadline, B&P Code Section 7068.1 provides a more generous 90-day window to account for the complexity of finding and vetting a new qualifier.
Option D: 60 days
60 days is a common wrong answer because it is close to 90 days but is not the correct statutory period. This distractor exploits the tendency to round down. The law is specific: it is 90 days, not 60.
Memory Technique
Think '90 days = one quarter to find your qualifier.' A business quarter is 3 months (roughly 90 days), giving the contractor one full business quarter to secure a replacement before the license suspends.
More law-business Questions
Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?
Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?
According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?
Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?
According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?
Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?
Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?
Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?
According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?
A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A California licensed contractor wants to form a joint venture with another licensed contractor for a specific project. According to CSLB regulations, what is required for this joint venture to legally perform contracting work?
Next Question
A subcontractor completed work on a private project on March 15th. The owner recorded a notice of completion on April 1st. What is the deadline for the subcontractor to record their mechanics lien?