According to California Civil Code Section 3247, what is the time limit for filing a stop payment notice on a private work project?
Correct Answer
B) 30 days after completion of work
California Civil Code Section 3247 establishes that a stop payment notice must be given not later than 30 days after completion of the work of improvement. This is a critical deadline for contractors and subcontractors to protect their payment rights on private construction projects.
Why This Is the Correct Answer
California Civil Code Section 3247 establishes a 30-day deadline for filing a stop payment notice after completion of the work of improvement on private projects. This 30-day window is a critical payment protection mechanism that allows contractors, subcontractors, and material suppliers to place a hold on construction loan funds held by a lender, preventing the owner from disbursing funds before payment claims are resolved.
Why the Other Options Are Wrong
Option A: 20 days after completion of work
20 days is the timeframe associated with the Preliminary Notice (20-Day Preliminary Notice) requirement — the notice that must be served early in a project to preserve lien and stop payment notice rights. Confusing the 20-day preliminary notice deadline with the 30-day stop payment notice deadline is the most common error on this topic.
Option C: 90 days after completion of work
90 days is the deadline for recording a mechanics lien on private work (90 days after completion of the project or the claimant's work, whichever is earlier). Confusing the mechanics lien deadline with the stop payment notice deadline is a frequent error, as both are post-completion deadlines related to payment protection.
Option D: 60 days after completion of work
60 days is not a standard deadline in California's private works payment protection framework. It does not correspond to any major milestone for stop payment notices, mechanics liens, or preliminary notices under the Civil Code.
Memory Technique
Remember the payment protection timeline as '20-30-90': 20 days to send Preliminary Notice (during project), 30 days to file Stop payment notice (after completion), 90 days to record mechanics lien (after completion). Visualize a countdown: 20 → 30 → 90. Stop payment notice = 30 days = middle number.
More law-business Questions
Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?
Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?
According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?
Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?
According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?
Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?
Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?
Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?
According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?
A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Under B&P Code Section 7159, Home Improvement Contractor requirements, what is the maximum time period a contractor has to commence work after a home improvement contract is signed before the homeowner's right of rescission expires?
Next Question
A California licensed contractor wants to form a joint venture with another licensed contractor for a specific project. According to CSLB regulations, what is required for this joint venture to legally perform contracting work?
