A wall assembly in Florida requires R-13 insulation. The contractor installs 3.5-inch thick fiberglass batts with R-11 value. What additional insulation is needed to meet the requirement?
Correct Answer
D) R-2 continuous insulation
The installed R-11 batts need an additional R-2 to reach the required R-13 total. This can be achieved with continuous insulation such as rigid foam board to minimize thermal bridging through the framing.
Why This Is the Correct Answer
The calculation is straightforward: Required R-value (R-13) minus installed R-value (R-11) equals additional insulation needed (R-2). The contractor must add R-2 continuous insulation, typically rigid foam board, to achieve the total R-13 requirement. Continuous insulation also helps reduce thermal bridging through the wall framing members, improving overall thermal performance of the wall assembly.
Why the Other Options Are Wrong
Option A: R-6 continuous insulation
R-6 continuous insulation would exceed the requirement. Adding R-6 to the existing R-11 batts would result in R-17 total insulation, which is 4 R-values more than the required R-13. This represents unnecessary material cost and potential construction complications.
Option B: R-13 continuous insulation
R-13 continuous insulation would double the required insulation value. Combined with the existing R-11 batts, this would create R-24 total insulation, far exceeding the R-13 requirement and representing significant material waste and cost overrun.
Option C: No additional insulation needed
Additional insulation is definitely needed since the installed R-11 batts fall short of the R-13 requirement by 2 R-values. The wall assembly would not meet Florida's energy code requirements without the additional insulation.
Memory Technique
Remember 'R-equired minus R-eceived equals R-emaining' - subtract what you have from what you need to find the gap.
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
