EstatePass
Business & FinanceAdminmedium26% of exam part

A subcontractor submits an invoice for completed work but fails to include required lien waivers. What should the general contractor do?

Correct Answer

C) Withhold payment until proper lien waivers are provided

Proper lien waivers are essential for protecting the owner and general contractor from potential lien claims. Payment should be withheld until all required documentation is properly submitted and executed.

Answer Options
A
Pay the invoice immediately to maintain good relationships
B
Contact the owner to determine if lien waivers are necessary
C
Withhold payment until proper lien waivers are provided
D
Pay 90% of the invoice and hold 10% until waivers are received

Why This Is the Correct Answer

Withholding payment until proper lien waivers are provided is the correct and legally prudent approach. Lien waivers protect both the general contractor and property owner from potential mechanic's lien claims by subcontractors or their suppliers. Florida law requires proper documentation before payment to ensure the contractor has legal protection. Making payment without proper lien waivers exposes the contractor to potential double payment if liens are later filed.

Why the Other Options Are Wrong

Option A: Pay the invoice immediately to maintain good relationships

Partial payment without proper lien waivers still exposes the contractor to full lien liability, and there's no legal basis for the arbitrary 90/10 split - proper documentation is required before any payment.

Option D: Pay 90% of the invoice and hold 10% until waivers are received

Paying immediately without lien waivers creates significant legal and financial risk, as the contractor could face mechanic's liens even after payment, potentially requiring double payment to clear title issues.

Memory Technique

Think 'WAIVER FIRST' - just like you wouldn't drive without insurance, don't pay without proper lien waivers protecting you from future claims.

Reference Hint

Florida Building Construction Standards - Chapter 713 (Mechanics' Liens) and contract administration sections

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.