A subcontractor submits a payment application for $85,000. After reviewing the work completed, you determine that only 80% of the claimed work is actually complete. If you typically retain 10% on all payments, what amount should be paid?
Correct Answer
A) $61,200
Earned amount = $85,000 × 80% = $68,000. After 10% retention: $68,000 × 90% = $61,200. The payment should be based on work actually completed, less the standard retention percentage.
Why This Is the Correct Answer
The calculation follows proper payment procedures: first determine earned amount ($85,000 × 80% = $68,000), then apply retention ($68,000 × 90% = $61,200). This ensures payment is based on actual work completed, not claimed work, and maintains the contractual 10% retention for project security and quality assurance.
Why the Other Options Are Wrong
Option B: $76,500
This amount ($76,500) incorrectly applies 10% retention to the full claimed amount ($85,000 × 90% = $76,500) without first adjusting for the actual work completed. It ignores the fact that only 80% of claimed work was verified as complete.
Option C: $68,000
This amount ($68,000) represents only the earned amount based on completed work ($85,000 × 80%) but fails to apply the required 10% retention. Retention must be withheld from all progress payments per standard construction contracts.
Option D: $85,000
This amount ($85,000) represents the full claimed amount without any adjustments. It ignores both the incomplete work status (only 80% complete) and the required 10% retention, violating proper payment administration procedures.
Memory Technique
Remember 'EARN then RETAIN': First calculate what was EARNED (completed work %), then apply RETENTION (subtract 10%). Never pay more than what's actually completed.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
