EstatePass
Business & FinanceAdminmedium26% of exam part

A subcontractor submits a payment application for $85,000. After reviewing the work completed, you determine that only 80% of the claimed work is actually complete. If you typically retain 10% on all payments, what amount should be paid?

Correct Answer

A) $61,200

Earned amount = $85,000 × 80% = $68,000. After 10% retention: $68,000 × 90% = $61,200. The payment should be based on work actually completed, less the standard retention percentage.

Answer Options
A
$61,200
B
$76,500
C
$68,000
D
$85,000

Why This Is the Correct Answer

The calculation follows proper payment procedures: first determine earned amount ($85,000 × 80% = $68,000), then apply retention ($68,000 × 90% = $61,200). This ensures payment is based on actual work completed, not claimed work, and maintains the contractual 10% retention for project security and quality assurance.

Why the Other Options Are Wrong

Option B: $76,500

This amount ($76,500) incorrectly applies 10% retention to the full claimed amount ($85,000 × 90% = $76,500) without first adjusting for the actual work completed. It ignores the fact that only 80% of claimed work was verified as complete.

Option C: $68,000

This amount ($68,000) represents only the earned amount based on completed work ($85,000 × 80%) but fails to apply the required 10% retention. Retention must be withheld from all progress payments per standard construction contracts.

Option D: $85,000

This amount ($85,000) represents the full claimed amount without any adjustments. It ignores both the incomplete work status (only 80% complete) and the required 10% retention, violating proper payment administration procedures.

Memory Technique

Remember 'EARN then RETAIN': First calculate what was EARNED (completed work %), then apply RETENTION (subtract 10%). Never pay more than what's actually completed.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.