A subcontractor files a Notice to Owner on a residential project valued at $85,000. The subcontractor's work is valued at $12,000. What is the maximum lien amount the subcontractor can claim under Florida Statute Chapter 713?
Correct Answer
A) $12,000
Under Florida Statute 713.06, a lienor can only claim a lien for the amount actually owed for their work, materials, or services. The subcontractor cannot claim more than the $12,000 value of their contracted work.
Why This Is the Correct Answer
Under Florida Statute 713.06, a lienor can only claim a lien for the actual amount owed for their specific work, materials, or services provided to the project. The subcontractor's work is valued at $12,000, which represents the maximum amount they can claim in a lien. The total project value is irrelevant to the individual subcontractor's lien rights - they cannot claim more than what they are actually owed for their portion of the work.
Why the Other Options Are Wrong
Option B: $17,000
Option A ($8,500) appears to be 10% of the total project value ($85,000), but there is no such percentage-based limitation in Florida lien law for subcontractors.
Option C: $8,500
Option C ($17,000) appears to be 20% of the total project value ($85,000), but Florida lien law does not limit subcontractor liens to a percentage of the total project value.
Option D: $85,000
Option D ($85,000) represents the total project value, but a subcontractor cannot claim a lien for the entire project value when their work only represents a portion of that total.
Memory Technique
Think 'You can only lien what you're owed' - the lien amount cannot exceed the actual debt owed to the lienor for their specific work.
Reference Hint
Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.06 regarding lien amounts and limitations
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
