A site plan shows existing grade at elevation 102.5 and proposed grade at elevation 104.0 at a specific point. What is the cut or fill requirement at this location?
Correct Answer
C) 1.5 feet of fill
Since the proposed grade (104.0) is higher than the existing grade (102.5), fill material is required. The difference of 1.5 feet indicates 1.5 feet of fill is needed at this location.
Why This Is the Correct Answer
The correct answer is B because when the proposed grade elevation (104.0) is higher than the existing grade elevation (102.5), additional material must be added to raise the ground level. This process is called 'fill.' The calculation is straightforward: 104.0 - 102.5 = 1.5 feet of fill material needed. Fill operations involve bringing in and compacting soil or other approved materials to achieve the desired final grade.
Why the Other Options Are Wrong
Option A: 1.5 feet of cut
Option D has the correct operation (fill) but uses an incorrect calculation of 6.5 feet instead of the actual difference of 1.5 feet.
Option D: 6.5 feet of cut
Option C is incorrect because it shows the wrong calculation (6.5 feet instead of 1.5 feet) and incorrectly identifies the operation as 'cut' when fill is needed.
Memory Technique
Use 'FILL UP' - when the proposed grade goes UP from existing, you need to FILL. Think of filling a hole to make it higher.
Reference Hint
Florida Building Code, Chapter 18 - Soils and Foundations, or site work sections in construction management references
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass