A site plan shows existing grade at elevation 102.5 and proposed grade at elevation 104.0 at a specific point. What is the cut or fill requirement at this location?

Correct Answer

C) 1.5 feet of fill

Since the proposed grade (104.0) is higher than the existing grade (102.5), fill material is required. The difference of 1.5 feet indicates 1.5 feet of fill is needed at this location.

Answer Options
A
1.5 feet of cut
B
6.5 feet of fill
C
1.5 feet of fill
D
6.5 feet of cut

Why This Is the Correct Answer

The correct answer is B because when the proposed grade elevation (104.0) is higher than the existing grade elevation (102.5), additional material must be added to raise the ground level. This process is called 'fill.' The calculation is straightforward: 104.0 - 102.5 = 1.5 feet of fill material needed. Fill operations involve bringing in and compacting soil or other approved materials to achieve the desired final grade.

Why the Other Options Are Wrong

Option A: 1.5 feet of cut

Option D has the correct operation (fill) but uses an incorrect calculation of 6.5 feet instead of the actual difference of 1.5 feet.

Option D: 6.5 feet of cut

Option C is incorrect because it shows the wrong calculation (6.5 feet instead of 1.5 feet) and incorrectly identifies the operation as 'cut' when fill is needed.

Memory Technique

Use 'FILL UP' - when the proposed grade goes UP from existing, you need to FILL. Think of filling a hole to make it higher.

Reference Hint

Florida Building Code, Chapter 18 - Soils and Foundations, or site work sections in construction management references

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.