A site plan shows contour lines at 2-foot intervals. If you need to calculate the slope between two points that are 100 feet apart horizontally and span 4 contour lines, what is the slope percentage?
Correct Answer
A) 8%
The vertical rise is 4 contour lines × 2 feet = 8 feet. The horizontal run is 100 feet. Slope percentage = (rise/run) × 100 = (8/100) × 100 = 8%.
Why This Is the Correct Answer
Option C is correct because slope percentage is calculated as (rise/run) × 100. The vertical rise is determined by multiplying the number of contour lines crossed (4) by the contour interval (2 feet), giving 8 feet of rise. With a horizontal distance of 100 feet, the calculation becomes (8/100) × 100 = 8%. This is a fundamental surveying and grading calculation that contractors must understand for proper site development.
Why the Other Options Are Wrong
Option B: 4%
Option A incorrectly uses only the number of contour lines (4) as the percentage without accounting for the 2-foot interval between lines or properly applying the slope formula.
Option C: 6%
Option D incorrectly calculates the slope by using 10 feet of rise instead of the correct 8 feet, possibly confusing the number of contour intervals with the actual elevation change.
Memory Technique
Remember 'RRH': Rise = contour lines × interval, Run = horizontal distance, then (Rise/Run) × 100 = slope percentage
Reference Hint
Look up site work and grading sections in your construction reference manual, typically found in earthwork or surveying chapters.
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?