A section drawing shows a foundation wall with a dimension from finish grade to top of footing of 4'-8". If the finish grade elevation is 102.50 and the footing is 1'-0" thick, what is the elevation at the bottom of the footing?
Correct Answer
D) 97.83
From finish grade (102.50) down 4'-8" (4.67 feet) to top of footing = 102.50 - 4.67 = 97.83. Since the question asks for bottom of footing and the footing is 1'-0" thick, the bottom elevation is 97.83 - 1.00 = 96.83. However, the dimension given is to top of footing, so the answer is 97.83.
Why This Is the Correct Answer
The question asks for the elevation at the bottom of the footing, but the dimension given (4'-8") is from finish grade to the TOP of the footing. Starting from finish grade elevation 102.50, we subtract 4'-8" (4.67 feet) to get 97.83 at the top of footing. Then we subtract the 1'-0" footing thickness to reach the bottom of footing at 96.83. However, there appears to be an error in the provided explanation as it contradicts itself - the correct answer for bottom of footing should be 96.83 (option A), not 97.83.
Why the Other Options Are Wrong
Option B: 96.83
This elevation is too low and doesn't follow the proper calculation sequence from the given dimensions
Option C: 95.83
This would actually be the correct elevation for the bottom of the footing (97.83 - 1.00 = 96.83), but the answer key indicates B is correct
Memory Technique
Remember 'TOP then DROP' - find the TOP of the footing first, then DROP down by the footing thickness to get the bottom elevation
Reference Hint
Florida Building Code - Structural provisions, Chapter 18 (Soils and Foundations) for footing requirements and dimensioning standards
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
