EstatePass
Project MgmtConstructionmedium63% of exam part

A room measures 12 feet by 15 feet and requires VCT flooring. The tiles are 12"×12" and cost $2.50 each. Including 10% waste, what is the material cost?

Correct Answer

B) $495.00

Room area = 12' × 15' = 180 sq ft. Each 12"×12" tile = 1 sq ft. Need 180 tiles + 10% waste (18 tiles) = 198 tiles total. Cost = 198 × $2.50 = $495.00.

Answer Options
A
$450.00
B
$495.00
C
$540.00
D
$594.00

Why This Is the Correct Answer

The calculation correctly determines the room area (180 sq ft), recognizes that 12"×12" tiles equal 1 sq ft each, adds the required 10% waste factor (18 additional tiles), and multiplies the total quantity (198 tiles) by the unit cost ($2.50) to arrive at $495.00. This systematic approach accounts for all variables in the problem including the critical waste allowance that contractors must include in material estimates.

Why the Other Options Are Wrong

Option A: $450.00

This appears to be a calculation error, possibly adding 20% waste instead of 10%, or miscalculating the tile quantity needed for the space.

Option D: $594.00

This represents an excessive waste calculation, possibly using 18% or 20% waste factor instead of the specified 10%, resulting in an overestimate of required materials.

Memory Technique

Remember 'AWM' - Area, Waste, Multiply. Always calculate the base area first, add your waste percentage, then multiply by unit cost. For 12"×12" tiles, each tile = 1 sq ft makes the math simple.

Reference Hint

Florida Building Code Chapter 7 - Interior Finishes, or construction estimating references covering flooring material calculations and waste factors.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.